Project Description
This project was undertaken by a consortium comprising dafabet.com mobile Engineering Consultants Group, Misr Engineering Development Company (MEDCOM), and ECM Energy Services.
The district dafabet.com mobile plant consists of a ground floor and a mezzanine, with a total built-up area of about 3,500 m2.
The plant, operated using chilled water, has a total dafabet.com mobile capacity of 16,866 kW (4,800 TR).
It includes the following components:
- double-height chiller yard complete with chillers, pumps, piping, and connections
- administration area that includes offices, meeting room, toilets, storage area, and other services
- electrical rooms with low-voltage and medium-voltage generators
The dafabet.com mobile has four centrifugal, water-cooled, parallel counterflow chillers, as well as HFC-134a refrigerants. The chillers utilize the vapor-compression cycle, and each chiller has a capacity of 2 × 5,622 kW (2 × 1,600 TR) at a
constant speed, and a capacity of 2 × 2,811 kW (2 × 800 TR) at a variable speed.
District dafabet.com mobile System
- Chilled water design temperature: 8.9 C°
- Chilled water supply/return: 4.4 C/13.3 C° Pumping
- Primary chilled water pumps: 4
- Secondary pumps: 4
Drive: variable speed
- Condensation pumps: 4
- Pump type: horizontal split case dafabet.com mobile Towers
- Position: atop the dafabet.com mobile
- dafabet.com mobile towers: 4
- Cells per dafabet.com mobile tower: two towers have two cells each, and two towers have one cell each
- dafabet.com mobile tower temperature: 5.6 C°
- dafabet.com mobile tower design temperature (in/out): 35.0 C°/29.4 C°
Activities
- Architectural
- Civil Works
- Communications and security systems
- Electrical
- HVAC
- Infrastructure
- Landscaping
- Mechanical
- Structural
Scope
- Shop drawings
Client
Egyptian Ministry of Defense