{"id":3039,"date":"2017-03-09T13:12:24","date_gmt":"2019-12-10T11:41:06","guid":{"rendered":"https:\/\/ecgsa.com\/?project=smart-village-school"},"modified":"2020-02-12T14:40:55","modified_gmt":"2020-02-12T14:40:55","slug":"smart-village-school","status":"publish","type":"project","link":"https:\/\/www.ecgsa.com\/project\/smart-village-school\/","title":{"rendered":"Smart Village School"},"content":{"rendered":"
On a plot area of 70,870 m2, the project was developed in 4 phases:<\/p>\n
The project also comprised playgrounds, fences, gates and car & bus parking area, as well as infrastructure.<\/p>\n
The main challenge was that the works had to be completed, tested, commissioned and operated at least one month before the beginning of the school year to allow the owner to start his activities such as furnishing
and fixing of equipment and apparatus, thus leaving only about eight months for construction, testing & commissioning. Accordingly a fast track construction procedure was adopted.<\/p>\n","protected":false},"featured_media":3040,"template":"","activity":[556,567,557,558,568,560,561,562,566],"country":[93,71,86],"scope":[638,640,641,645,637],"sector":[227,240],"yoast_head":"\n