{"id":4893,"date":"2017-04-19T12:25:10","date_gmt":"2019-12-10T12:04:24","guid":{"rendered":"https:\/\/ecgsa.com\/?project=al-shabab-gas-turbine-generating-plant"},"modified":"2020-02-12T14:40:37","modified_gmt":"2020-02-12T14:40:37","slug":"al-shabab-gas-turbine-generating-plant","status":"publish","type":"project","link":"https:\/\/www.ecgsa.com\/project\/al-shabab-gas-turbine-generating-plant\/","title":{"rendered":"Al-Shabab Gas Turbine Generating Plant"},"content":{"rendered":"
Kharafi National (KN) was awarded the Engineering, Procurement and Construction (EPC) contract of Egypt Al-Shabab Gas Turbine Generating Plant (GTGP). ECG was invited by KN to provide the engineering design services in support to their EPC contract.<\/p>\n
The first gas turbine unit started commercial operation on June, 2011 for Al-Shabab GTGP. Subsequently, ECG set its fast track methodology to fully complete the design services in a period satisfying KN proposed schedule requirements.<\/p>\n
The new plant has eight new gas turbines with a total rated capacity of 1,000 MW using 8*125 MW gas turbines.<\/p>\n
Understanding the importance, sensitivity and urgency for implementing the plant within the time constraint being a national “on spot” project, ECG quickly set a task force from its senior staff to plan and set the project staffing requirements and the immediate mobilization of task forces, fast-track quality control measures, and packaging of deliverables which were tailored to meet KN milestones, enabled the quick start of construction and allowed for a continuous flow of KN construction execution scheme.<\/p>\n
ECG Scope of Services covered the following:<\/p>\n