{"id":5447,"date":"2019-01-31T10:16:59","date_gmt":"2019-12-10T12:13:56","guid":{"rendered":"https:\/\/ecgsa.com\/?project=irrigation-potable-water-lines-for-the-new-capital"},"modified":"2022-08-30T07:54:38","modified_gmt":"2022-08-30T07:54:38","slug":"irrigation-potable-water-lines-for-the-new-capital","status":"publish","type":"project","link":"https:\/\/www.ecgsa.com\/project\/irrigation-potable-water-lines-for-the-new-capital\/","title":{"rendered":"Irrigation & Potable Water Lines for the New Capital"},"content":{"rendered":"
The project aims to convey potable water to the New Capital. The project is executed over three parts:<\/p>\n
First Part: Construction of Water Line<\/strong> From the strategic, water-reservoir pump station to Project 110<\/p>\n Second Part: Potable Water from New Cairo Water Plant<\/strong><\/p>\n Aiming to transfer potable water from New Cairo Water Plant to the Valleys Area in the New Capital and Project 110. Third Part: Completing Irrigation Lines’ Works<\/strong>
From the storage tanks lift station to the strategic reservoir lift station as follows:<\/p>\n\n
\n
This part consists of two pipelines with a diameter of 1,000 mm for each, conveying 250,000 m3<\/sup>\/day, and is divided into two groups:<\/p>\n\n
This project comprises the following:<\/p>\n\n