{"id":8433,"date":"2022-03-03T11:29:14","date_gmt":"2022-03-03T11:29:14","guid":{"rendered":"https:\/\/www.ecgsa.com\/?post_type=project&p=8433"},"modified":"2022-08-30T08:22:01","modified_gmt":"2022-08-30T08:22:01","slug":"road-bridge-and-radial-spine-in-n4-area-jodp","status":"publish","type":"project","link":"https:\/\/www.ecgsa.com\/project\/road-bridge-and-radial-spine-in-n4-area-jodp\/","title":{"rendered":"Road Bridge and Radial Spine in N4 Area (JODP)"},"content":{"rendered":"
The project comprises a road bridge, Radial Spine (2), and a storm water network in N4 area. It aims at providing an access to the four zones (N4-1 to N4-4) by constructing the bridge that connects the north part of project to the south part. The bridge has a length of 101.5 m and width of 15 m. The bridge height is the same as the Road a Tunnel at level +312. Additionally, a roundabout at the end of the bridge allows the vehicles to turn around safely.<\/p>\n
Due to cancelation of Mussalah building, a Radial Spine (2) is designed to allow access to N4-3 and N4-4 areas.<\/p>\n
Also, the storm water storage is located in N4-3 area to collect storm water from Radial Spine 1 and Radial Spine 2. Water collection is done by shifting the tanks, manholes, and pipes\u2019 networks out of N4 area.<\/p>\n
Utilities serving the four zones (N4-1 to N4-4) occupy a technical gallery (TG) that is located below the road level to accommodate dry and wet utilities.<\/p>\n","protected":false},"featured_media":8443,"template":"","activity":[556,558,568,559,571,561,562,566],"country":[171],"scope":[638,645,637,649],"sector":[264,263],"yoast_head":"\n